Effective Change Order Management

This article discusses factors resulting from Change Orders that influence project performance and costs, calculation methods for estimating the cost of a potential Change Order, procedures for initiating a Change Order, Successful negotiation and finalization of a Change Order, and more.

Effective Change Order Management

ABSTRACT: The preparation, estimation, and resolution of Change Orders can present challenges to any engineering and construction project. The all-too-common practice of ignoring, delaying, or taking a prejudicial approach to the processing and resolution of Change Orders can potentially lead to distrust between the parties while the issues remain unresolved. This inappropriate practice often results in an interruption in the flow of the work, an increase in the costs of the project, delays to contract milestones, and possibly an extended date for project completion.

Change Orders can also become unmanageable if the process is not sufficiently defined, or if the individuals involved in the preparation and administration of the Change Orders on a project are inexperienced. As is often the case, claims and disputes occur when the Change Orders on a project are not properly addressed. Therefore, the proper management of Change Order issues is key to a project’s success.

The following topics are discussed:

1. CHANGE ORDER DEFINITION AND OTHER CHANGE ORDER-RELATED CONSIDERATIONS

A Change Order is a document that contractually alters an original agreement between the signed parties. Relative to construction, a Change Order is the result of an owner-approved revision to terms and conditions (e.g., scope of work, timeframe for performance, price, etc.) that are defined in a contract for a project.

Comparatively, Field Work Orders (FWO) are directives from an engineer or construction manager that either clarify or request minor changes to the contract documents. FWOs are typically minor revisions that usually do not have a significant impact the contract budget or schedule.

Change Orders can be either directed by the owner or requested by the contractor. Depending upon its specific requirements, a change may or may not impact a project’s contractual cost and schedule. In the circumstances that the cost is affected, a change may be represented as either an increase or a credit. Similarly, the durations of activities in a project schedule that are identified with a change may be extended or reduced. If these activities are on the schedule’s critical path, the date for the completion of a project may be impacted.

It is important that the scope of the work for the project be completely defined in the contract so that disagreements over scope changes can be minimized. However, it is common on projects that the parties find disagreement over what scope or factors may comprise a change order and/or its impact. This disagreement is not unusual because the nature of each change will predictably affect each party in different ways.

The resolution and management of Change Orders can also become the source of disputed issues between the owner and the contractor on projects. The disputed issues become further intensified if the change order management process is inadequately handled. The owner’s and the contractor’s diverging and competing interests relative to the changes on a project may also become a factor in judiciously resolving the differences.

The owner’s priorities are focused on predicting and controlling the costs so that the funding, which is budgeted for a project, does not become jeopardized. Also, the owner usually places a high priority on achieving a certain completion date for the project, and often will include contractual liquidated damages to be paid by the contractor if the contractual completion date is not achieved, absent any delays for which the contractor may be entitled to a time extension.

For the contractor, Change Orders entail several factors, which can be potentially complicated. First, Change Orders are often viewed as a means of increasing the scope of a project and offer a source of additional revenue. However, this supplemental work can also present the contractor with the problem of having to proceed with the completion of change-related scope of work prior to negotiating and finalizing the entitlement and payment for a change. The contract may require the contractor to proceed with the extra work pending the resolution of the valuation of a Change Order, which may also require the contractor to finance the cost of the alleged additional work until resolution occurs. The contractor will normally proceed with scope changes if it is confident that it will be fairly compensated for the alleged extra work at a later date. The contractor also has an incentive to complete the contract work in a timely manner because “time equals money,” i.e., the contractor’s field staff and other time-related costs continue to rise if the contract work is delayed beyond its planned completion date.

Construction contracts often include conflicting clauses regarding changed work. On one hand, a contract may state that the contractor cannot proceed with the work for a change in the absence of a written and approved construction Change Order. On the other hand, language in a contract may also state that the owner has the right to order the contractor to perform extra work without an agreement for compensation. These conflicting clauses place the contractor in a position of having to make a choice between performing the extra work at the risk of having to later possibly accept a reduced payment, no payment, or making the decision to refuse to proceed with completing the work. The later choice, however, may place the contractor in a position of default, which could possibly result in the contractor being terminated on a project by the owner.

2. FACTORS THAT ESTABLISH A CHANGE ORDER

A number of different factors can influence the development of Change Orders on projects. These elements can result from either foreseen or unforeseen conditions and include, but are not limited to the following:

3. CHANGE ORDER BACKLOG

It is advantageous to both the owner and the contractor that potential Change Orders on a project are processed in a fair, equitable, and timely manner. The failure to do so most often results in an increased probability of extended disputes and claims between the owner and the contractor.

A significant amount of Change Order backlog, in terms of quantity and value, is indicative of a project that is in trouble. The backlog is typically attributed to the above-average submission of Change Order Requests by the contractor and/or the owner’s inability or reluctance to promptly process the potential Change Orders.

A large backlog of unresolved potential Change Orders generally falls into one of the following categories:

4. FACTORS RESULTING FROM CHANGE ORDERS THAT INFLUENCE A PROJECT’S PERFORMANCE AND COSTS

There are numerous elements that can influence the cost of a Change Order. The work for Change Orders can necessitate that the contractor redirect the labor, material, and equipment resources that were originally budgeted, scheduled, and designated to be used to support the completion of the tasks identified for the contract scope of work. As a result, the contractor’s plan for completing the project may be impacted. The factors from Change Orders that may affect the planned performance of a project include the following:

5. METHODS FOR CHANGE ORDER BASIS OF CALCULATION

The pricing for potential Change Orders can be developed using one of several methods. The choice of method can be established by the contract, from a post contract agreement between the owner and the contractor, or at the contractor’s discretion. Each of the methods has distinct advantages and disadvantages that are dependent upon the nature of a project and the requirements specific to the given change. The pricing is typically based on one of the following practices:

6. PROCEDURES FOR INITIATING A CHANGE ORDER

The contract typically provides that either the owner or the contractor is entitled to introduce a Change Order. The procedures for initiating a Change Order have a tendency to differ between projects, as owners and construction managers each have their own established requirements and preferences. Although there may be some variances, the following items address the practices that are normally expected on a project.

An important step in the initiation process is for the originator to classify whether the change is required or elective, and for the owner to confirm and approve this designation. The determination of whether a change is required or elective will influence the justification for the change and how the change will be evaluated. The differences between the two classifications include the following: